Project Overview
During the March 2022 Severe Storm Event a section of a major roadway experienced landsliding on the downslope road embankment causing closure of the east bound traffic lane.
Our Role
As part of the remediation works RGS was tasked with providing emergency design rectification and detailed design for permanent works.
The option of a soil nail and rockfill slope was selected for the remediation works.
Project Challenges
Challenges for the project included:
- Minimising property impacts – The site was located adjacent to culturally sensitive land;
- Access – Access to the site was limited and required specialist plant and equipment; and
- Staging of works and minimising the impacts to road users.
Project Deliverables
The detailed design and reporting included:
- Preparation of design reports including slope modelling and construction staging works.
- Preparation of detailed design drawings in CAD format.
- Recommendations on materials specifications and hold points.
- Safety in design analysis.

Project Outcomes
The key outcomes realised by this project include:
- Future proofing the section of road from further downslope instability; and
- Improved road safety for all road users.
Related Projects
More regional NSW projects from our team.
Flood Damage Remediation Works
Byabarra NSW
Landslide Remediation Works
Glenugie to Tyndale, Pacific Highway NSW
Cutting Remediation Works
Cangai Cutting, Gwydir Highway (Bruxner Highway)
Rockfall Protection Works
Waterfall Way between Bellingen & Dorrigo, NSW
Bridge Replacement
Mitchells Flat NSW
Temporary Design Works
Glenugie to Tyndale, Pacific Highway NSW