Project Overview
The design and construction of this Multi Storey Building at Coffs Harbour were challenging due to the site being situated at the transition between the residual hills to the west and marine sands to the east.
Our Role
As part of the project, RGS worked to undertake the investigation works which transitioned into providing advice during the construction phase.
Project Challenges
Challenges for the project included: Managing the shallow groundwater; Installing pre support for excavations adjacent to adjacent properties; and Minimising impacts to adjacent properties during piling.
Due to the variable subsurface conditions beneath the site many different foundation types were considered including grout injected, cased bored, driven piles, and screw piles. From a construction and cost perspective the screw pile option was selected for design.

Project Outcomes
The detailed design and reporting included: Preparation of geotechnical reports including piling recommendations and design parameters; and Construction monitoring works, construction staging, observing the screw pile installation works to meet the required materials and founding depths, release of piling hold points.
Related Projects
More regional NSW projects from our team.
Historic House Restoration
Lake Macquarie NSW
Bridge Replacement
Mitchells Flat NSW
Temporary Design Works
Glenugie to Tyndale, Pacific Highway NSW
Bridge Foundation & Temporary Works Design
Romiaka Bridge, Clarence Valley NSW
Contamination Assessment and Remediation
MidCoast NSW
Contamination Investigation & Remediation
Tuncurry NSW