Project Overview
During bulk earthworks for a large development on the NSW Mid-North Coast, contamination was encountered in the form of foreign materials within existing uncontrolled fill on the site.
Our Role
RGS were engaged to undertake a site contamination assessment, prepare a Remedial Action Plan, and undertake validation testing of the remaining soils.
Project Challenges
Presence of large volume of uncontrolled imported fill requiring evaluation from a contamination perspective for future residential land use. Asbestos Containing Material (ACM) contamination present required remediation and validation work.
Project Outcomes
Completed and directed remediation involving removal and disposal of ACM impacted fill to render site suitable for future residential land use.