Project Overview
The Sewerage Treatment Plant upgrade involves the construction and installation of several infrastructure assets to increase wastewater treatment capacity and performance. The works include an IDEA Reactor comprising a dual-cell concrete tank approximately 5.5m deep along with a UV disinfection system and effluent pump station. Supporting facilities include a blockwork blower building, switchroom, rotary drum thickeners and a chemical dosing and storage area.
Our Role
RGS provided geotechnical investigation and assessment for the infrastructure upgrades to assist with concept design.
Our scope included assessment of foundation conditions, excavation conditions, pavement design parameters and pavement thickness designs.
Project Challenges
Depth to rock varied significantly over the site leading to differing excavation conditions for each structure. High strength rock exposures were observed at the surface in a portion of the site with deep alluvial and residual profiles in others with no rock encountered in some boreholes to depths of 7m.
Subgrade materials in proposed pavement areas generally comprised high plasticity, low CBR, moderately reactive materials which will have poor trafficability when stripped, during wet weather.

Project Outcomes
Our geotechnical investigation and assessment provided a detailed overview of conditions at the site. Foundation and earthworks recommendations were provided for each structure which allowed informed decision-making during the concept design phase.
The results of the geotechnical assessment reduces the likelihood of unexpected conditions and allows more accurate tendering and programming during construction phases.